Virtual Tour
Graduate Studies
Materials Science and Engineering
Chemical Engineering
Environmental Engineering
Biotechnology and Food Engineering
Physics
Mathematics with Computer Science
Chemistry
Mechanical Engineering (Robotics)
Research Overview
- Research Centers
MATEC
Electron Microscopy Center
X-ray Laboratory
ChE & EnvE Central Lab
BFE Core Facility
Chemistry Analytical Instrumentation Core
- Researchers
- Research Fellowship
- GTEC
Campus EHS
IT Services
Academic Technologies
Undergraduate Studies
- Mainland Chinese Students
- Hong Kong, Macau and Taiwan Students
- International Students
Graduate Studies
PostTime:1/18/2017

On January 16th, 2017, integral hoisting of the steel truss (with a 46-meter span) above the main campus entrance was completed successfully, which is one of the construction difficulties.
Steel structure is adopted for the whole Administrative Building and a part of the Education Building, with the main campus entrance in between. Assembled from 600 steel members, this long-span steel truss weighs around 560 tons with a span of 46 meters and a height of 6 - 8 meters.
According to the construction party, two-tier steel truss of the connective corridor was assembled on the ground and then four lifting points (load-bearing: 200 tons/ point) were set on the top of the truss. Special steel strands were used to connect the points and the hoist, which composed a hydraulic lifting system for integral hoisting. Installation of the lower truss began when the truss was hoisted up to 5 meter, after which the truss continued to be lifted to the planned height.
To guarantee construction quality, the construction party exercised strict control over both the whole and the partial size of the truss and conducted stress-strain & displacement monitoring during assembly and hoisting, as well as estimating its stress states according to real-time data. Ground and low-altitude assembly and welding provided convenience for machine weld and reduce aloft work. The adoption of hydraulic lifting also ensured the security and progress of the construction.